BUILDING CHRONOLOGY

Retyped from 1914 "General Information 'U.S.S. TEXAS', finished plans 37 & 38 "

June 24, 1910 Authorization by Act of Congress
September 27, 1910 Advertisement approved by the Navy Department
December 1, 1910 Bids received and opened
December 17, 1910 Contract signed, $5,830,000; 
December 17, 1913 Contract date of completion
December 24, 1910 Plans and specifications delivered to the Contractor
December 27, 1910 First hull material ordered
January 16, 1911 Lines faired in the mould loft
January 19, 1911 First hull material received
April 17, 1911 Keel laid
April 21, 1911 First frame erected
May 5, 1911 First transverse bulkhead erected
July 1 1911 First large casting received
August 5 1911 First large casting erected (stern post)
August 7, 1911 First armor plate received (Central Armor)
August 7, 1911 First armor plate installed (Central Armor)
September 14, 1911 First compartment tested
May 14, 1912 Rudder installed
May 18, 1912 Ship launched
September 3, 1912 Ship first docked at Norfolk Navy Yard
February 22, 1913 First turret installed (Structure)
March 5, 1913 First 14" gun installed
August 5, 1913 First 5" gun installed
October 21-29, 1913 Official sea trial
February 21, 1914 Final inclining experiment
March 10, 1914 Last armor plate installed
March 12, 1914 Delivery at Norfolk Navy Yard
March 12, 1914 Commissioned